Retrofit: replacement of bucket elevators and capacity increase

250 t/h
Capacity
2023
New bucket elevators for a improved process

In addition to a wear-related necessity to replace the bucket elevators, an increase in performance was the goal of the project. Both the disassembly and the assembly were entirely in the hands of Zuther GmbH. The elevators extend over eight floors and have a total height of 45 meters. In particular, the tight space conditions in the plant posed a challenge to our assembly team.

In a nutshell
  • Location: Germany
  • Exchange bucket elevators
  • Capacity increase to 250 t/h
  • 8 floors – 45 meters total height
  • Assembly and disassembly by Zuther
/